Tuesday, 29 November 2022

November S&T Report.

›
 Unfortunately things are moving so fast by the time this is published it will most likely be out of date. There is currently two large proj...
Tuesday, 15 November 2022

Dalfaber Monday of week 3

›
At the end of play on Monday night we are into the third week of the Dalfaber project. With more visible signs of the New Crossing becoming ...

External renovation of the Speyside Signal Box at Aviemore

›
  External renovation of the  Speyside  Signal Box at  Aviemore  over   11 & 12 th  November . By Colin Frost A request had been made fo...
Saturday, 12 November 2022

Boat of Garten South project

›
Along with all the work been done at Dalfaber. Work is also progressing at Boat of Garten South.  The lead off table at Boat South has been ...

Dalfaber report for mid week night shift 9th November

›
New Rails and sleepers through the Crossing Deck Area installed on Wednesday Nightshift together with Under Road ducts for Signalling and po...

Dalfaber weekend work 2nd November

›
After last week's P Way night shift the Contractor's focus has been on completing the North side footway which has seen steady progr...
Friday, 4 November 2022

Dalfaber night shift

›
Overall, a successful night shift with the planned work of achieving new sleepers spaced to receive the new deck panels on the North side of...
‹
›