S&T August Works Update
By Robert Law
Once again it’s time for show and tell. With the school holidays now just passed. Progress has been slower, but still productive. With works centred around Boat of Garten. The lift bar is now completed and ready for use, once other components of the project have caught up. The yard points have had a make over. Now they comply fully with our specifications for switch openings, free wheel clearance and residual openings. Lots of time and effort has gone into this. Which looking at it, is hard to tell. Thanks must be given to all who have helped. But if you have time to spare, please get in contact. Come along, have a chat. A cup of tea and if you are able to, get involved.
LMS 5025 passing the top of our worksite, with the afternoon run back to Aviemore. |
With the stretcher bar placed in the p-ways Rotabroach. With the first hole drilled and the second one ready to be drilled. A very simple job when you have good tools that are well maintained. |
With work continuing on the lift bar. All the parts that make up the bar, have been fishplated together. Holes drilled and attached to the clips, mounted on the rails. At this point, it was time for a test! Which was very successful as you can see. Once oiled, greased and moved a few more time after this recording. It became very light and easy to operate.
Looking the opposite way from the points. With a full view of the newly finished 50ft lift bar. |