Monday 31st October.
A selection of pictures from earlier today.
Old Crossing disconnected and recoveries underway. All poles now down on the North side and all tree stumps removed in the adjacent Amenity area.
Construction of new pavement on North side of road progressing.
Several Ballast Trains passed through the Worksite in connection with the Lighting Up Shed spoil removal works....
Traffic Management appears to be working well within minimal delay to road traffic and bus services. That could change if the Council restart Traffic Management at the Grampian Road Dalfaber Drive Junction......
No accidents or injuries. Contractors staff on site 7am to 7