At the end of play on Monday night we are into the third week of the Dalfaber project. With more visible signs of the New Crossing becoming evident around the site. Yesterday saw the first concert been poured on the site. This was for the YO Road Traffic Lights Signal base. With the same batch of concrete the foundation for the Electrical Supply cubical (SSE meter cabinet) was made. As the day was coming to an end the foundation concrete for the edge beams to the new level crossing deck on the North side of the Road were also laid.
|
First of the concrete been poured for the road lights. |
|
Power cubical been set up. |
|
Foundations for the power cubical been laid. |
|
Top been cleaned off. |
|
Foundations of the edge beams been laid |