After last week's P Way night shift the Contractor's focus has been on completing the North side footway which has seen steady progress.
north side pavement under construction. |
Purple duct is being installed for new Highland Council funded streetlighting which part of the project.
Meanwhile, over the weekend, SR staff installed the new Down Direction Advance Warning Board at approx. 84 Miles 130yards which is around 335 metres from the crossing and is part of our scope to deliver.
On Tuesday 8th November, the new Equipment Room to house the Level Crossing control circuitry was inspected at the Unipart Rail Signalling Installation facility in Gresty Road, Crewe. The building, having only recently arrived from the manufacturer in County Tyrone, fully met the Strathspey specification which was agreed back in May.
New REB ready to be fitted out at Unipart. |