Saturday 12 November 2022

Dalfaber report for mid week night shift 9th November

New Rails and sleepers through the Crossing Deck Area installed on Wednesday Nightshift together with Under Road ducts for Signalling and power cables.

New rails and sleepers installed, still to be raised to new height.

Cable ducts installed during the day shift.

Manhole chambers installed Thursday and concreted in Thursday Nightshift meaning we now have a continuous underground duct under the Track and under the Road.

New cable chamber connecting the duct.

New Rubber Deck Panels have arrived in our Yard and the VR video showing how to install can be viewed in the following link

New strain units now delivered ready to be installed. When the time is right.


No comments:

Post a Comment